50% REVIEW PROCESS
|
Project Deliveries & Objectives
|
OWASP Spanish Project's Deliveries & Objectives
|
QUESTIONS
|
ANSWERS
|
1. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please exemplify writing down those of them that haven't been realised.
|
- Full translation to Spanish of all the release-level document projects. Notice they include both pages and documents:
- Top 10 2007 - document translated.
- Guide 2 - to be started.
- Testing Guide - document translated.
- Legal - document translated.
- FAQ - document translated.
- Full Translation of major sections of OWASP Site (only pages)
- Project Main Pages - in progress.
- Principles (missing) - to be started.
- References Section (missing) - to be started.
- Conferences (missing) - to be started.
- News (missing) - to be started.
- About OWASP (missing) - to be started.
- Evaluation of Spanish translation approach for WebGoat and WebScarab and delivery of this document to Bruce and Rogan for possible implementation in near future. - in progress.
- Leverage for deploy of es.owasp.org, the domain already exists but is not redirecting correctly. - completed.
|
2. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please quantify in terms of percentage.
|
- Full translation to Spanish of all the release-level document projects. Notice they include both pages and documents:
- Top 10 2007 - 100% completed.
- Guide 2 - 0% completed.
- Testing Guide - 100% completed.
- Legal - 100% completed.
- FAQ - 100% completed.
- Full Translation of major sections of OWASP Site (only pages)
- Project Main Pages - 50% completed.
- Principles (missing) - 0% completed.
- References Section (missing) - 0% completed.
- Conferences (missing) - 0% completed.
- News (missing) - 0% completed.
- About OWASP (missing) - 0% completed.
|
3. Please do use the right hand side column to provide advice and make work suggestions.
|
The site domain es.owasp.org needs to be activated but it is expected to happen in the following days. As an overall score the project is currently at 60% completed.
|