50% REVIEW PROCESS | ||
---|---|---|
Project Deliveries & Objectives |
||
QUESTIONS | ANSWERS | |
1. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please exemplify writing down those of them that haven't been realised. |
Project deliverables are: move LiveCD to SLAX; update toolset, including documentation. Status is that LiveCD has been moved to SLAX (Beta LiveCD has been provided - it boots and passes basic functionality tests). Updated toolset on the Beta CD is currently under detailed test. Further documentation and tool iteration remain. | |
2. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please quantify in terms of percentage. |
Percentage completion status: move LiveCD to SLAX - 100% complete; update toolset, including documentation: 60% complete. | |
3. Please do use the right hand side column to provide advice and make work suggestions. |
Note: developer is ahead of schedule - has significantly passed the 50% completion point. Remaining work includes: further needs analysis of additional tool needs based on the testing methodology the LiveCD is to support; the addition of updated OWASP-specific test documentation, and the possible addition of a few high-quality tools (pending outcome of the needs analysis). |