50% REVIEW PROCESS | ||
---|---|---|
Project Deliveries & Objectives |
OWASP Classic ASP Security Project's Deliveries & Objectives | |
QUESTIONS | ANSWERS | |
1. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please exemplify writing down those of them that haven't been realised. |
The project has five main tasks, being them:
| |
2. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please quantify in terms of percentage. |
As stated before, we have five main work packages. Two of them already delivered in June, the first and main completed up to %53. We have missing two full work packages at this stage:
| |
3. Please do use the right hand side column to provide advice and make work suggestions. |
Project indicators such communication, task assessment, timing and effort has been managed very well. The project author delivered full documentation at all time. We have confidence things will continue the same way: Smooth and controlled. |