There will be a number of different schedules that need to be created
 
There will be a number of different schedules that need to be created
* Pre-Summit Schedule -  Created/Released 4 weeks before the Summit, Contains what its known at the time, doesn't make ANY commitment (apart for very specific exceptions) on when a Track or Working Session will occour, defines the KEY Summit Schedule components (i.e. how many Large/Medium/Small Working Sessions slots will  exist)
+
* Pre-Summit Schedule -  Created/Released 4 weeks before the Summit, Contains what its known at the time, doesn't make ANY commitment (apart for very specific exceptions) on when a Track or Working Session will occour, defines the KEY Summit Schedule components (i.e. how many Large/Medium/Small Working Sessions slots will  exist)  
 +
* Draft Scheadule - Not for public consumtions schedule, used internall to test out the possible schedule combinations and to detect/address major schedule conflicts
 +
* Final Schedule - Released 1 or 2 days before the Summit
 +
 
 +
 
 +
 
 +
 
 +
* Other items to take into account
 +
** Ask key attendees if they have remote meetings that they '''need''' to be and will make them unavailable to participate in a working session (we should keep these to the minimum, but it will be good to take them into account)
 +
** Some attendees will have other Summit Related tasks (let's say Jim with helping out on Podcasting), so we need to take this into account when creating the personalized scheadules

Revision as of 11:26, 11 January 2011

NOTE: THIS PAGE CURRENTLY CONTAINS A BRAIN DUMP (Jim please edit and delete this NOTE when you are happy with its content)

Discussion group

There is a dedicated Discussion Forum for Summit Schedule items, which can be found here: https://groups.google.com/a/owasp.org/group/summit-2011-schedule

Concepts

The key objecives of the Summit Schedule are:

  • Maximize Attendees productivity (while at the Summit)
  • Attract as much talent (and key players) to the Summit as possible
  • Convince attendees to spend (at least) 3 days at the Summit (Tue, Wed and Thu)

Schedules

There will be a number of different schedules that need to be created

  • Pre-Summit Schedule - Created/Released 4 weeks before the Summit, Contains what its known at the time, doesn't make ANY commitment (apart for very specific exceptions) on when a Track or Working Session will occour, defines the KEY Summit Schedule components (i.e. how many Large/Medium/Small Working Sessions slots will exist)
  • Draft Scheadule - Not for public consumtions schedule, used internall to test out the possible schedule combinations and to detect/address major schedule conflicts
  • Final Schedule - Released 1 or 2 days before the Summit



  • Other items to take into account
    • Ask key attendees if they have remote meetings that they need to be and will make them unavailable to participate in a working session (we should keep these to the minimum, but it will be good to take them into account)
    • Some attendees will have other Summit Related tasks (let's say Jim with helping out on Podcasting), so we need to take this into account when creating the personalized scheadules