(New page: == Open WebMail Assessment Progress - 75% == The bulk of the application security assessment is complete. Currently, we are working on the draft report that will be used to notify the Ope...)
 
Line 1: Line 1:
== Open WebMail Assessment Progress - 75% ==
+
== Open WebMail Assessment Progress - 80% ==
  
 
The bulk of the application security assessment is complete. Currently, we are working on the draft report that will be used to notify the Open WebMail developers.
 
The bulk of the application security assessment is complete. Currently, we are working on the draft report that will be used to notify the Open WebMail developers.
Line 8: Line 8:
 
:* '''Application Security Assessment Execution, 6 weeks''' - complete
 
:* '''Application Security Assessment Execution, 6 weeks''' - complete
 
:* '''Student Application Security Finding Write-ups, 2 weeks''' - complete
 
:* '''Student Application Security Finding Write-ups, 2 weeks''' - complete
:* '''Draft Report''' - near completion
+
:* '''Draft Report''' - complete
 
:* '''Open WebMail Notification''' - pending
 
:* '''Open WebMail Notification''' - pending
 
:* '''Final Report''' - pending
 
:* '''Final Report''' - pending

Revision as of 01:15, 30 August 2007

Open WebMail Assessment Progress - 80%

The bulk of the application security assessment is complete. Currently, we are working on the draft report that will be used to notify the Open WebMail developers.

  • Student Training and Preparation, Day 1 - complete
  • Student Training and Preparation, Day 2 - complete
  • Student Training and Preparation, Day 3 - complete
  • Application Security Assessment Execution, 6 weeks - complete
  • Student Application Security Finding Write-ups, 2 weeks - complete
  • Draft Report - complete
  • Open WebMail Notification - pending
  • Final Report - pending