50% REVIEW PROCESS | ||
---|---|---|
Project Deliveries & Objectives |
||
QUESTIONS | ANSWERS | |
1. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please exemplify writing down those of them that haven't been realised. |
The project contains 122 work packages grouped in three main elements:
| |
2. At what extent have the project deliveries & objectives been accomplished? Having in consideration the assumed ones, please quantify in terms of percentage. |
Overal site translation is %50 approximately. Tools are being studied on how to perform the translation in accordance to the tools authors and then translation will be required. Alpha level pages are mostly completed. Beta pages is half way to deliver. | |
3. Please do use the right hand side column to provide advice and make work suggestions. |
Work is being leaded by the author trough a mailing list that has many members already, all looks fine although translation is a hard work and requires extensive reviewing. The work can be forecasted (words/time) and i think that's the approach the leader is taking in order to make sure they will make on time. |